Decision Maker: Assistant Director Housing and Building Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Resume the full Housing planned maintenance
programme for both 20/21 and 21/22. These were approved at cabinet
on 20/02/2020 and 18/02/2021 respectively. Safe systems of work
have been established in line with government guidance.
Financial/staffing/health & safety (incl virus transmission
risks)/service delivery impacts/other risks and impacts
considered:
We have been working closely with Health & Safety and Public
Health colleagues to establish updated risk assessment and method
statements. This will allow the work to be carried out safely for
both operatives and tenants.
Those shielding will be given the opportunity to opt out of the
programme and be reinstated at a later date.
Equality Impacts:
None
To resume all planned capital programmes that
have been delayed due to covid restrictions as approved at council
in February 2020 & February 2021.
Reason: Work programme agreed by Council and further delays are
resulting in an increase in costly repairs where the products have
reached their end of life.
N/A
Publication date: 27/04/2021
Date of decision: 26/04/2021