Decision Maker: Assistant Director Housing and Building Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To carry out structural repairs to Council
properties in accordance with safe working practices. Work was put
on hold on a temporary basis during the full lockdown period.
Financial/staffing/health & safety (incl virus transmission
risks)/service delivery impacts/other risks and impacts
considered:
Updated risk assessment and method statements will allow this work
to be carried out safely for both operatives and tenants.
To carry out structural repairs and
improvements to council properties in the areas of Hundens Lane,
Havelock Street and Park Place commencing from August 2020.
Reason: Work programme was agreed by Council in March 2020 and
structural improvements are important to protect our tenant’s
safety and the fabric of our buildings.
None.
Publication date: 23/11/2020
Date of decision: 17/06/2020