Decision Maker: Assistant Director Highways and Capital Projects
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Retaining wall being built as part of the
Haughton Throughabout project is almost complete with just the
facia stone to put in place which will take two weeks
maximum.
Hall Construction who are the sub-contractors carrying out the work
and have asked if they could start back on site to complete this
element of the works.
Once this walling is complete then it opens up a large amount of
footway/cycleway work for our own construction teams which would
give us a good start when we return to site.
We have requested a full set of RAMS which will be vetted and
approved to ensure they will be adhering to the social distancing
rules while carrying out this work and we will have a site manager
on site at all times to monitor this.
Completing this piece of work now with two men only on site will
mean less operatives on site to monitor when construction teams
return.
Financial/staffing/health & safety (incl virus transmission
risks)/service delivery impacts/other risks and impacts
considered:
Programme - Up to two weeks work for two operatives
COVID19 - The works can be progressed under the current guidelines
with the necessary systems in place. The footway Is currently
closed and fenced off so there can be no contact with the
public.
Equality Impacts:
Not applicable.
To allow Subcontractor to restart on site w/c
4th May ahead of main project restart to phase recommencement under
supervision of DBC staff. (Subject to satisfactory methods of
working being agreed).
Reason: To enable gradual re-commencement and management of
resources on site.
To leave this element of work until site teams
return to work although this would mean an extra two operatives on
site.
Publication date: 23/11/2020
Date of decision: 13/05/2020