Decision Maker: Managing Director
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Request to waive contract procedure rules and
agree direct contract award in respect of road construction to new
build site to Wearmouth Construction.
That the contract procedure rules be waived
and direct contract award be agreed in respect of road construction
to new build site to Wearmouth Construction for a contract term of
12 months at a cost of £144,000.
Reason - Works have started with the Contractor and the award is to
ensure completion on the works.
None.
Publication date: 26/03/2021
Date of decision: 15/10/2019