Tees Valley Energy Recovery Facility Local Authority Special Purpose Vehicle

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

For Members to approve the Local Authority Special Purpose Vehicle (LA-SPV) and the Inter-Authority Agreement 2 (IAA2)

Decisions:

The Cabinet Member with the Local Services Portfolio introduced the report of the Group Director of Services (previously circulated) providing an update to Members on all aspects of the Tees Valley Energy Recovery Facility (TV-ERF) project; outlining the rationale for setting up the Local Authority Special Purpose Vehicle (LA-SPV); how the LA-SPV will be governed; and the commercial principles as to how costs and liabilities shall be shared between the seven Councils over the term of the Project.

 

The submitted report stated that this Council had joined with Durham County Council, Hartlepool Borough Council, Middlesbrough Council, Newcastle City Council, Redcar and Cleveland Borough Council and Stockton Borough Council, to procure a contractor to design, build, operate and finance a new Energy Recovery Facility to be located in the Tees Valley, servicing the waste of 1.5m residents; outlined the current waste / treatment contracts for each of the seven authorities which were due to expire in 2025/26; stated that a new Residual Waste Treatment Contract was required to be procured to allow for a new facility to be constructed and fully commissioned in preparation for the commencement date for the new service of 1 April 2026; and that the contract would terminate on 31 March 2052 unless both parties agreed to an extension.

 

It was reported that the procurement process was being undertaken in accordance with the Public Procurement Regulations 2015 (as amended); the OJEU Notice to commence the procurement process was issued on 24 July 2020; supported by Business Cases, the requirement was for a 450,000 tonne per annum Energy Recovery Facility (ERF) with Combined Heat and Power (CHP) capability to treat the Councils’ municipal solid waste; the combined tonnage unlocked economies of scale; the Tees Valley Energy Recovery Facility (TV-ERF) would be designed to have a minimum 40-year lifespan; the Contractor appointed would build, finance and operate the ERF; the initial contract term would commence in 2022 to enable construction of the facility; and that a 22-acre brownfield site, owned by South Tees Development Corporation (STDC), had been selected within the Teesworks regeneration site to locate the facility.

 

It was also reported that a Local Authority Special Purpose Vehicle (LA-SPV) (a Limited Company) was required to be formed by the seven Councils; the regulation and management of the LA-SPV would be governed by a Shareholders’ Agreement (SHA); and that each Council (Shareholder) would be required to formally enter into the Shareholders’ Agreement approximately three months in advance of the Project Agreement being entered into with the successful Contractor (Financial Close).

 

Particular references were made to the Waste Supply and Support Agreement (WSSA) which would govern the terms of the commercial arrangements between the seven Councils (the Shareholders) in relation to the LA-SPV; the target date for completion of the procurement process; and the governance of the project.

 

A member of the public in attendance at the meeting made reference to the possible inclusion, by the Government, of incineration in the Emissions Trading Schemes (ETS) and enquired whether calculations had been done to factor in ETS costs and their impact and whether there was a evidence that 450,000 tonnes of incineration capacity would be required.  References were made at the meeting to the fact that municipal waste was not included in the definition of energy from a renewable source in the Renewable Energy Directive; the carbon emissions from the facility; how the on-going reductions in emissions would be captured and what sanctions would the company face should they not be met; concerns around the bottom ash produced by the facility; carbon capture; and the implications should the economies of scale not be met.  The Cabinet Member with the Local Services Portfolio responded thereon.

 

RESOLVED   (a)  That the creation of a Local Authority Special Purpose Vehicle (LA-SPV), which will be the contracting body for the seven Councils with the successful contractor, be approved, and the Assistant Director Community Services be appointed as a Director of the LA-SPV.

(b)  That the Council enter into the Shareholders Agreement and authority be delegated to the Group Director of Services to finalise the agreement, in consultation with the Cabinet Member for Local Services.

 

(c)  That it be noted that the Council will be entering into a service level agreement with Redcar and Cleveland Borough Council as the host Authority to provide support services to the LA-SPV.

 

(d)  That the Council enter into the Waste Supply and Support Agreement with the LA-SPV, and authority be delegated to the Group Director of Services to finalise the agreement, in consultation with the Cabinet Member for Local Services.

 

(e)  That authority be delegated to the LA-SPV to enter into contract with the successful contractor at financial close and to enter into a 50-year lease with South Tees Development Corporation (Teesworks) for the site.

 

(f)  That authority be delegated to the Group Director of Services, in consultation with the Cabinet Member for Local Services, to enter into two guarantees, the first for the LA-SPV and the second to underwrite the LA-SPV’s obligations under the 50-year lease for the site.

 

(g)  That authority be delegated to the Group Director of Services, in consultation with the Cabinet Member for Local Services, to finalise and agree the business plan for the LA-SPV.

 

(h)  That authority be delegated to the Group Director of Services, in consultation with the Cabinet Member for Local Services, to finalise and agree an equalisation agreement between the Tees Valley Authorities for the transfer and bulk transportation of material to the TV-ERF.

REASONS – (a)  The current waste contract has already been extended and cannot be extended further as this could potentially breach procurement regulations.  The other Tees Valley Councils are in a similar position.

 

(b)  It is essential the Tees Valley Councils have in place a contract for the treatment of the residue of waste once recyclable materials have been removed.  This will provide diversion of waste from landfill and maximise the recovery of energy and any residues.

 

(c)  The recommendations are the necessary steps to move forward the Tees Valley Energy Recovery Facility project.

 

(d)  By procuring the development of the Tees Valley Energy Recovery Facility together with other Councils, this Council will be able to ensure the construction of a purpose designed modern facility within the region and be able to benefit from economies of scale.

Report author: Charleen Dods

Publication date: 08/04/2022

Date of decision: 05/04/2022

Decided at meeting: 05/04/2022 - Cabinet

Effective from: 20/04/2022