Agenda item

Project Position Statement and Capital Programme Monitoring - Quarter 2 - 2024/25

Report of the Executive Director - Environment, Highways and Community Services and the Executive Director - Resources and Governance. .

Minutes:

The Cabinet Member with the Resources Portfolio introduced the report (previously circulated) of the Executive Director – Environment, Highways and Community Services and the Executive Director – Resources and Governance providing the latest Capital resource and commitment position, to inform monitoring of the affordability and funding of the Council’s capital programme; an update on the current status of all construction projects currently being undertaken by the Council; and requesting that consideration be given to a number of changes to that programme.

 

The submitted report stated that the projected outturn of the current capital programme was £331.717m against an approved programme of £332.202m; the investment was delivering a wide range of improvements to the Council’s assets and services; the programme, including commitments, remained affordable within the Medium Term Financial Plan (MTFP) for 2024/25 to 2027/28; the Council was managing 26 live projects, with an overall projected outturn value of £157.489m, the majority of which were running to time, cost and quality expectations, but were being monitored given the current pressures on resources in the construction sector nationally; and that the projects were managed either by the Council’s in-house management team, a Framework Partner or by Consultants sourced via an open/OJEU tender process.

 

RESOLVED - (a) That the status position on construction projects, as detailed in the submitted report, be noted.

 

(b) That the projected capital expenditure and resources, as detailed in the submitted report, be noted.

 

(c) That the adjustments to resources, as detailed in paragraph 21 of the submitted report, be approved.

 

REASONS - (a) To inform Cabinet of the current status of construction projects.

 

(b) To make Cabinet aware of the latest financial position of the Council.

 

(c) To maintain effective management of resources