Report of the Managing Director and the Director of Economic Growth and Neighbourhood Services
Minutes:
The Cabinet Member with the Efficiency and Resources Portfolio introduced the report of the Director of Economic Growth and Neighbourhood Services (previously circulated) providing a summary of the latest Capital resource and commitment position, to inform monitoring of the affordability and funding of the Council’s capital programme; an update on the current status of all construction projects currently being undertaken by the Council; and requesting that consideration be given to a number of changes to the programme.
The submitted report stated that the projected outturn Capital Programme was £171.913M against an approved programme of £171.567M; the investment was delivering a wide range of improvement, to the Council’s assets and services; the programme remained affordable within the Medium Term Financial Plan (MTFP) for 2018/19 to 2021/22; there were currently 30 live projects currently being managed by the Council with an overall value of £69.748M; the majority of those projects were running to time, cost and quality expectations with no foreseeable issues; and that the projects were managed either by the Council’s in-house management team, a Framework Partner or by Consultants sourced via an open/OJEU tender process.
RESOLVED – (a) That the status position on construction projects, as detailed in Appendix 1 of the submitted report, be noted.
(b) That the projected capital expenditure and resources, as detailed in the submitted report, be noted.
(c) That the adjustments to resources, as detailed in paragraph 19 of the submitted report, be approved.
REASONS – (a) To inform Cabinet of the current status of construction projects.
(b) To make Cabinet aware of the latest financial position of the Council.
(c) To maintain effective management of resources.