NOTE - APPLICATIONS FOR PLANNING PERMISSION – The following standard conditions are referred to in those Minutes granting permission or consent :-

 

Code No.

Conditions

CL1

Prior to the commencement of the development and any site investigative works a Phase 1 Preliminary Risk Assessment shall be prepared by a "suitably competent person(s)" and submitted to and agreed in writing with the Local Planning Authority. The Phase 1 Preliminary Risk Assessment shall include a Site Inspection and a Conceptual Site Model (CSM) to identify and illustrate all potential contamination sources, pathways and receptors associated with the site and the surrounding environment.

Reason - The site may be contaminated as a result of past or current uses and/or is within 250 metres of a site which has been landfilled and the Local Planning Authority wishes to ensure that the proposed development can be implemented and occupied with adequate regard to environmental and public protection

CL2

Prior to the commencement of the development and any site investigation works or at a time agreed in writing by the Local Planning Authority a Phase 2 Site Investigation Strategy (Sampling and Analysis Plan) shall be designed and documented by a "suitably competent person(s)" in accordance with published technical guidance (e.g. BS10175 and CLR11) and be submitted to and agreed in writing with the Local Planning Authority, unless the Local Planning Authority dispenses with the requirement specifically and in writing.  The Phase 2 Site Investigation Strategy (Sampling and Analysis Plan) shall be sufficient to fully and effectively characterise and evaluate the nature and extent of any potential contamination sources, hazards and impacts.  No alterations to the agreed Phase 2 Site Investigation Strategy or associated works shall be carried out without the prior written agreement of the Local Planning Authority.

Reason - The site may be contaminated as a result of past or current uses and/or is within 250 metres of a site which has been landfilled and the Local Planning Authority wishes to ensure that the proposed development can be implemented and occupied with adequate regard to environmental and public protection.

CL3

Prior to the commencement of the development or at a time agreed in writing by the Local Planning Authority a Phase 2 Site Investigation works shall be conducted, supervised and documented by a “suitably competent person(s)” and carried out in accordance with the approved Phase 2 Site Investigation Strategy (Sampling and Analysis Plan).  A Phase 2 Site Investigation and Risk Assessment Report prepared by a “suitably competent person(s)”, in accordance with published technical guidance (e.g. BS10175 and CLR11) and shall be submitted to and agreed in writing with the Local Planning Authority unless the Local Planning Authority dispenses with the requirement specifically and in writing.

Reason - The site may be contaminated as a result of past or current uses and/or is within 250 metres of a site which has been landfilled and the Local Planning Authority wishes to ensure that the proposed development can be implemented and occupied with adequate regard to environmental and public protection

CL4

Prior to the commencement of the development or at a time agreed in writing by the Local Planning Authority a Phase 3 Remediation and Verification Strategy shall be prepared by a "suitably competent person(s)" to address all human health and environmental risks associated with contamination identified in the Phase 2 Site Investigation and Risk Assessment. The Remediation and Verification Strategy which shall include an options appraisal and ensure that the site is suitable for its new use, and shall be submitted to and agreed in writing with the Local Planning Authority, unless the Local Planning Authority dispenses with the requirement specifically and in writing. No alterations to the Remediation and Verification Strategy or associated works shall be carried out without the prior written agreement of the Local Planning Authority.

The Phase 3 Remediation and Verification works shall be conducted, supervised and documented by a "suitably competent person(s)" and in accordance with the approved Phase 3 Remediation and Verification Strategy.

Reason - The site may be contaminated as a result of past or current uses and/or is within 250 metres of a site which has been landfilled and the Local Planning Authority wishes to ensure that the proposed development can be implemented and occupied with adequate regard to environmental and public protection

CL5

Any contamination not considered in the Phase 3 Remediation and Verification Strategy, but identified during subsequent construction/remediation works shall be subject to further risk assessment and remediation proposals agreed in writing with the Local Planning Authority and the development completed in accordance with any further agreed amended specification of works.

Reason - The site may be contaminated as a result of past or current uses and/or is within 250 metres of a site which has been landfilled and the Local Planning Authority wishes to ensure that the proposed development can be implemented and occupied with adequate regard to environmental and public protection

CL6

A Phase 4 Verification and Completion Report shall be complied and reported by a "suitably competent person(s)", documenting the purpose, objectives, investigation and risk assessment findings, remediation methodologies and validation results obtained to demonstrate the completeness and effectiveness of all approved remediation works conducted.  The Phase 4 Verification and Completion Report and shall be submitted and agreed in writing with the Local Planning Authority within 2-months of completion of the development unless the Local Planning Authority dispenses with the requirement specifically and in writing. 

The development site or agreed phase of development site, shall not be occupied until all of the approved investigation, risk assessment, remediation and verification requirements relevant to the site (or part thereof) have been completed, reported and approved in writing by the Local Planning Authority.

Reason - The site may be contaminated as a result of past or current uses and/or is within 250 metres of a site which has been landfilled and the Local Planning Authority wishes to ensure that the proposed development can be implemented and occupied with adequate regard to environmental and public protection