Minutes:
NOTE - APPLICATIONS FOR PLANNING PERMISSION – The following standard conditions are referred to in those Minutes granting permission or consent:-
Code No. |
Conditions |
A3 |
Implementation Limit (Three Years) The development hereby permitted shall be commenced not later than the expiration of three years from the date of this permission. Reason - To accord with the provisions of Section 91(1) of the Town and Country Planning Act, 1990. |
B4 |
Notwithstanding any description of the external materials in the submitted application, details of the external materials to be used in the carrying out of this permission (including samples) shall be submitted to, and approved by, the Local Planning Authority in writing prior to the commencement of the development and the development shall not be carried out otherwise than in accordance with any such approved details. Reason - In order that the Local Planning Authority may be satisfied as to the details of the development in the interests of the visual amenity of the area. |
C5 |
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking or re?enacting that Order), no enlargement, improvement or other alteration of the premises, including any additional structures/building within the curtilage of the site, shall be carried out without the prior consent of the Local Planning Authority, to whom a planning application must be made. Reason - In order not to prejudice the amenities of the adjoining properties and in order that the Local Planning Authority is able to exercise control over future development of the site. |
PL |
The development hereby permitted shall be carried out in accordance with the approved plan(s) as detailed below, ^IN; Reason - To define the consent. |
E2 |
A landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority prior to any works commencing and, upon approval of such schemes, it shall be fully implemented concurrently with the carrying out of the development, or within such extended period as may be agreed in writing by, the Local Planning Authority, and thereafter any trees or shrubs removed, dying, severely damaged or becoming seriously diseased shall be replaced, and the landscaping scheme maintained for a period of five years to the satisfaction of the Local Planning Authority. Reason - To ensure a satisfactory appearance of the site and in the interests of the visual amenities of the area. |
(1) Planning Permission Granted
18/00591/FUL - Land adjacent Oak Tree Pub off Yarm Road Middleton St George, Darlington. Variation of condition 3 (Approved Plans) attached to planning permission 16/01256/FUL dated 19 June 2018 for residential development comprising 12 No. dwellings (Revised scheme) - to permit the substitution of house types and amended layout.
(In reaching its decision, the Committee took into consideration the Planning Officer’s report (previously circulated) and the views of the applicant’s agent, an objector and a representative of the Parish Council, all of whom Members heard).
RESOLVED – (a) That, subject to
the completion of a deed of variation to the Section 106 Agreement
relating to 16/01256/FUL within six months of the date of this
meeting, to ensure that the obligations contained therein attached
to this permission and, subject to the following conditions,
planning permission be granted :-
1.
The development hereby permitted shall be commenced
not later than 18 months from the date of this permission.
Reason - To accord with the provisions of 92(2) of the Town
and Country Planning Act 1990 and to ensure the speedy provision of
the site for the approved development.
2. B4 (Materials).
3.
PL00 (Accordance with approved plans)
Site layout plan 2018/OAK/100
House detail plans 2018/OAK/101 and 2018/OAK/102
4. E2 (Landscaping).
5. Prior to the occupation of any unit within the development, a scheme for the provision of affordable housing shall be submitted to and approve in writing by the local planning authority. The provision will take the form of on-site provision (of not less than 20% of the housing units) in accordance with a scheme to be submitted and agreed in writing by the local planning authority. The scheme for the development shall include:
(a) The timing of the construction of the affordable housing and its phasing in relation to the occupancy of the market housing;
(b) The arrangements for the transfer of the affordable housing to an affordable housing provider (or the management of the affordable housing) (if no RSL is involved);
(c) The arrangements to ensure that such provision is affordable for both first and subsequent occupiers of the affordable housing;
(d) The occupancy criteria to be used for determining the identity of occupiers of the affordable housing and the means by which such occupancy criteria shall be enforced;
(e) The affordable housing shall be provided in accordance with the approved scheme and shall meet the definition of affordable housing in Annex 2 of the National Planning Policy Framework or any future guidance that replaces it.
Reason – To comply with Core Strategy Policy CS11.
6.
Precise details of the
off-site highway works required to access the site and mitigate the
development impact shall be submitted and approved by the Local
Planning Authority prior to the commencement of the
development. The submitted details shall include widening of
the existing footway along the north-south section of Oak Tree
Close to 2.0m wide, the addition of a new footway along the
frontage of the development on the east-west section of Oak Tree
Close at 2.0m wide (measured between restraints) connecting into
the surrounding infrastructure and the new site access junction and
linking footways. The development shall not be carried out
otherwise than in complete accordance with the approved
details.
Reason – In the interests of highway
safety.
7.
Prior to the commencement of the development, a Construction
Management Plan shall be submitted and approved in writing by the
Local Planning Authority. The Plan shall include details for wheel
washing, a dust action plan, the proposed hours of construction,
vehicle routes, road maintenance, and signage. The
development shall not be carried out otherwise than in complete
accordance with the approved detail.
Reason – In the interests of residential
amenity.
8.
Development shall not
commence until a detailed scheme for the disposal of foul and
surface water from the development hereby approved has been
submitted to and approved in writing by the Local Planning
Authority in consultation with Northumbrian Water and the Lead
Local Flood Authority.
Reason – To prevent the increased risk of
flooding from any sources in accordance with the NPPF.
9. The development hereby approved shall not be commenced on site, until a scheme for ‘the implementation, maintenance and management of a Sustainable Surface Water Drainage Scheme has first been submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented and thereafter managed and maintained in accordance with the approved details, the scheme shall include but not be restricted to providing the following details:
(a) Detailed design of the surface water management system;
(b) A build program and timetable for the provision of the critical surface water drainage infrastructure;
(c) A management plan detailing how surface water runoff from the site will be managed during the construction phase;
(d) Details of adoption responsibilities.
Reason - To ensure the site is developed in a manner that will not increase the risk of surface water flooding to site or surrounding area, in accordance with the guidance within Core Strategy Development Plan Policy CS10 and the National Planning Policy Framework.
10. The buildings hereby approved shall not be brought into use until:-
(a) Requisite elements of the approved surface water management scheme for the development, or any phase of the development are in place and fully operational to serve said buildings;
(b) A Management and maintenance plan of the approved Surface Water Drainage scheme has been submitted and approved in writing by the Local Planning Authority, this should include the funding arrangements and cover the lifetime of the development.
Reason - To reduce flood risk and ensure satisfactory long term maintenance are in place for the lifetime of the development.
That,
subject to the Section 106 Agreement not being completed within the
prescribed period without the written consent of the Council to
extend this time, the minded to approve status of this permission
shall be considered to be a refusal on the grounds that the
application has failed to provide adequate mitigation measures to
provide a satisfactory form of development in accordance with the
requirements of Core Strategy Policy CS4 (Developer Contributions)
without any further reference to the Planning Applications
Committee.
18/00810/FUL - Durham Tees Valley Airport. Construction of 1.8km link road between Northside and Southside, erection of 2.8m high security fencing, and associated infrastructure; and improvements and alterations to the existing highway (resubmission of previously approved scheme) (additional drainage information received 27 September 2018).
(In reaching its decision, the Committee took into consideration the Planning Officer’s report (previously circulated) and the views of a representative of the Parish Council who Members heard).
RESOLVED - That planning permission be granted subject to the following conditions:
1. A3 (Standard 3 year time limit).
2. PL00
(a) General Arrangement, drawing number DTVA01-ARP-HW-01-DR-CH-00001 Issue 4;
(b) Typical Fencing Details, drawing number DTVA01-ARP-HW-03-DR-CH-000002 Issue 0;
(c) Proposed Highway Widening, drawing number DTVA01-ARP-HW-01-DR-CH000002 Issue 1;
3.
No
construction/building works or deliveries shall be carried out
except between the hours of 0800 and 1800 hours on Mondays to
Fridays and between 0900 and 1300 hours on Saturdays. There shall be no construction activity including
demolition on Sundays or on Bank Holidays.
Reason – To ensure that the development does
not prejudice the enjoyment of neighbouring occupiers or their
properties.
4. The development hereby approved shall not be commenced on site, until a scheme for the implementation, maintenance and management of a sustainable surface water drainage scheme has first been submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented and thereafter managed and maintained in accordance with the approved details, the scheme shall include but not be restricted to providing the following details:
(i) Detailed design of the surface water management system;
(ii) A build program and timetable for the provision of the critical surface water drainage infrastructure;
(iii) A management plan detailing how surface water runoff from the site will be managed during the construction phase;
(iv) Details of adoption responsibilities
Reason – To ensure the site is developed in a manner that will not increase the risk of surface water flooding to site or surrounding area, in accordance with the guidance within Core Strategy Development Plan Policy CS10 and the National Planning Policy Framework.
5. The development permitted by this planning permission shall only be carried out in accordance with the approved Flood Risk Assessment (FRA) and Drainage Strategy dated August 2018 and the following mitigation measures detailed within the FRA:
(i) Discharge limited to 3.8 l/s/ha
(ii) Discharge location is existing outfall no. 4
The mitigation measures shall be fully implemented
prior to the occupation and subsequently in accordance with the
timing/phasing arrangements embodied within the scheme, or within
any period as may subsequently be agreed, in writing by the Local
Planning Authority.
Reason – To prevent flooding by ensuring the
satisfactory storage of/disposal of surface water from the site and
to reduce the risk of flooding to the proposed development and
future occupants.
6. The building hereby approved shall not be brought into use until:
(i) Requisite elements of the approved surface water management scheme for the development, or any phase of the development are in place and fully operational to serve said building;
(ii) A management and maintenance plan of the approved Surface Water Drainage scheme has been submitted and approved in writing by the Local Planning Authority, this should include the funding arrangements and cover the lifetime of the development.
Reason – To reduce flood risk and ensure satisfactory long term maintenance are in pace for the lifetime of the development.
7.
A Construction Management Plan shall be submitted to
and agreed in writing by the Local Planning
Authority prior to the commencement of development
to agree the routing of all HGV movements associated with the
construction phases and to effectively control dust emissions from
the site works, this shall address earth moving activities, control
and treatment of stock piles, parking for use during construction
and measures to protect any existing footpaths and verges, vehicle
movements, wheel cleansing, sheeting of vehicles, offside
dust/odour monitoring and communication with local residents.
Reason – In the interests of the occupiers of adjacent
and nearby premises and highway safety.
8. Prior to the commencement of development a scheme for the ground preparation works consisting of soil stripping of arable topsoil to reduce nutrient levels, drainage works to ensure a free draining soil (except in agreed areas which may provide wetland habitat in the non-turf trans located areas) for the receptor site to ensure the success of grassland habitat creation shall be submitted to and approved in writing by the Local Planning Authority. Such a scheme shall include:
(i) The precise delineation and location of the area to be a minimum of 3.67ha which shall include turf translocation of the 2.03 ha to be lost from situ and additional creation of 1.64ha through green hay and seed planting;
(ii) Details of the timing for the delivery and works (to ensure breeding birds are not affected) of the long-term maintenance and management of the site which shall include for the duration of the establishment of the receptor site and the subsequent remediation/maintenance, management and monitoring of the receptor site for the lifetime of the development.
The development shall be carried out in accordance with the approved details to the reasonable satisfaction of the Local Planning Authority.
Reason – To ensure the identified ecological impact of the proposed development is appropriately mitigated.
18/00784/FUL - Studio Below 6A West Row, Sadberge. Change of use from writing studio to 1 No. bedroom dwelling including association of 1 No. separate garage accessed from Church Lane.
(In reaching its decision, the Committee took into consideration the Planning Officer’s report (previously circulated) and the views of the applicant’s representative whom Members heard).
RESOLVED - That planning permission be granted subject to the following conditions :-
1. A3 (Standard 3 year time limit).
2. PL00 (approved plans condition).
(a) Proposed floor plan, drawing no. 7, dated 22.8.18
(b) Proposed south west elevation, drawing no. 9, dated 22.8.18
(c) Proposed north east elevation, drawing no. 10, dated 22.8.18
(d) Proposed south east elevation, drawing no. 11, dated 22.8.18
3. C5 (removal of PD rights).
4.
Notwithstanding the provisions of the Town and
Country Planning (General Permitted Development) (England) Order
2015 (or any order revoking and re?enacting that Order) no fencing,
walls or other means of enclosure shall be erected without the
prior written consent of the Local Planning Authority to whom a
planning application must be made.
Reason - In the interest of visual amenity.
Supporting documents: