21/00688/DC– Demolition of existing
buildings and erection of station building with concourse,
multi-storey car park, transport interchange, public realm and
highways works and alterations to boundary wall (Additional Bat
Survey Report received 27 August 2021).
(In reaching its decision, the Committee
took into consideration the Planning Officer’s report
(previously circulated), the views of the Council’s
Highways
Officer, Environmental Health Officer, Rights of Way Officer,
Sustainable Transport Officer and Conservation Officer; the views
of Northern Gas Networks, Northumbrian Water, Northern PowerGrid,
Durham County Council Archaeology Team, and the Local Lead Flood
Authority; the concerns expressed by Historic England; the views of
Network Rail; the concerns raised by the British Transport Police
and the Durham Constabulary Architectural Liaison Officer; the
views of Darlington Association on Disability; five letters of objection; the
objections of the Friends of the Stockton and
Darlington Railway, and the views of the Applicant’s Agent, whom the
Committee heard).
RESOLVED – That Planning Permission
be granted subject to the following conditions:
- A3 –
Implementation Limit (Three Years).
- The
development hereby permitted shall be carried out in
accordance with the approved plans, as detailed below:
a)
SGMSCP-NAP-Z1-ZZ-DR-A-00001 P2 - Location
Plan
b)
SGMSCP-NAP-Z1-00-DR-A-00010
P5 – Site Plan
c)
SGMSCP-NAP-Z0-XX-DR-A-90001 P6 – Landscape
General Arrangement
d)
SGMSCP-NAP-Z1-00-DR-A-01000 P11 – Level
00-01
e)
SGMSCP-NAP-Z1-02-DR-A-01002 P9 - Level
02-03
f)
SGMSCP-NAP-Z1-04-DR-A-01004 P9 - Level
04-05
g)
SGMSCP-NAP-Z1-06-DR-A-01006 P9 - Level
06-07
h)
SGMSCP-NAP-Z1-08-DR-A-01008 P9 - Level
08-09
i)
SGMSCP-NAP-Z1-XX-DR-A-02000 P5 - East
Elevation
j)
SGMSCP-NAP-Z1-XX-DR-A-02001 P5 - North East
Elevation
k)
SGMSCP-NAP-Z1-XX-DR-A-02002 P5 - North West
Elevation
l)
SGMSCP-NAP-Z1-XX-DR-A-02003 P5 - South East
Elevation
m)
SGMSCP-NAP-Z1-XX-DR-A-02004 P5 - West Elevation
n)
SGMSCP-NAP-Z1-XX-DR-A-02005 P5 - South Elevation
o)
SGMSCP-NAP-Z1-XX-DR-A-03000 P15 - GA Sections Block A
p)
SGMSCP-NAP-Z1-XX-DR-A-03001 P14- GA Sections Block B
q)
SGMSCP-NAP-Z1-XX-DR-A-03002 P6 - GA Sections Station
r)
SGMSCP-NAP-Z0-XX-DR-A-00020 P4 - Site Sections
s)
SGMSCP-FHT-Z0-SL-DR-C-00001 P5 - Proposed Drainage Layout
t)
SGMSCP-FHT-Z0-SL-DR-C-00101 P3 - S278 Works General Arrangement
u)
SGMSCP-FHT-Z0-SL-DR-H-00002 P4 - Non Motorised User Plans
v)
SGMSCP-FHT-Z0-SL-DR-H-00005 P4 - Areas of highway to be Stopped
w)
SGMSCP-FHT-Z0-SL-DR-H-00007 P4 - Proposed Access Arrangements
x)
SGMSCP-FHT-Z0-SL-DR-H-00008 P4 - Garbutt Sq. Swept Path
y)
SGMSCP-FHT-Z0-SL-DR-H-00009 P3 - Access Swept Path
z)
SGMSCP-FHT-Z0-SL-DR-H-00010 P3 - Access Arrangements Swept Path
aa)
SGMSCP-FHT-Z0-SL-DR-H-00011 P3 - Garbutt Sq. Swept Path
bb)SGMSCP-FHT-Z0-SL-DR-H-00012 P3 -
Stopping Up Plan
REASON – To ensure the
development is carried out in accordance with the planning
permission
- No building shall be
constructed above damp proof course until precise details of the
materials to be used throughout the development (buildings and
public realm) hereby approved have been submitted to and approved
in writing by the Local Planning Authority. The development shall
not be carried out otherwise than in complete accordance with the
approved details
REASON - In the interests of the visual appearance of the
development.
- No building shall be
constructed above damp proof course until precise details of a
lighting scheme for the development has been submitted to and
approved in writing by the Local Planning Authority. The
development shall not be completed otherwise than in complete
accordance with the approved details.
REASON - In the interests of the
visual appearance of the development and the wider street scene,
residential amenity and to protect biodiversity.
- Prior to the
demolition of the stone retaining wall on Neasham Road/Parkgate,
precise details of the design and materials to be used in the
replacement means of enclosure shall be submitted to and approved
in writing by the Local Planning Authority. The development shall
not be carried out otherwise than in complete accordance with the
approved details.
REASON - In the interests of the
visual appearance of the development.
- No building shall be
constructed above damp proof course until a landscaping scheme has
been submitted to and approved in writing by the Local Planning
Authority. The details shall include a management plan for the
scheme and upon approval of such scheme, it shall be fully
implemented concurrently with the carrying out of the development,
or within such extended period as may be agreed in writing by, the
Local Planning Authority, and thereafter any trees or shrubs
removed, dying, severely damaged or becoming seriously diseased
shall be replaced, and the landscaping scheme maintained for a
period of five years to the satisfaction of the Local Planning
Authority.
REASON - To ensure a satisfactory
appearance of the site and in the interests of the visual amenities
of the area.
- No building shall be
constructed above damp proof course until fully detailed highway
design information has been submitted to and approved in writing by
the Local Planning Authority. The information shall include the
precise details of all works within the public highways and works
intended for adoption by the Highways Authority. Details should
include phasing of works, material specifications, surface
finishes, tie-in details, construction standards/pavement makeup.
Details should also include level/gradient information of all
pavements and roads. Precise details of signing and lining works.
The development shall not be carried out otherwise than in complete
accordance with the approved details
REASON - In the interests of highway
safety.
- No building shall be
constructed above damp proof course until vehicle swept path
analysis has been undertaken to support the movement framework for
emergency vehicles, refuse vehicles and buses, for the internal
network and, where appropriate, in respect of the off-site highway
proposals, details of which shall be submitted to and approved by
the Local Planning Authority
REASON - In the interests of highway
safety.
- A Road Safety Audit
shall be carried out for all of the highways and the scope of the
Audit shall be agreed in writing with the Local Planning Authority.
The development shall not be carried out unless in complete
accordance with the approved Audit.
REASON - In the interests of highway
safety.
- No building shall be
constructed above damp proof course until precise details of the
cycle storage building have been approved have been submitted to
and approved in writing by the Local Planning Authority. The
details shall include the number of cycles, the location and design
of the building, the type of cycle stan, security measures and the
future maintenance of the building. The cycle stand shall be in
place prior to the occupation of the building and retained
thereafter. The development shall not be carried out otherwise than
in complete accordance with the approved details.
REASON - In the interests of promoting
sustainable modes of transport
- No buildings shall be
built above damp-proof course level, until a scheme of proposals
for reducing carbon emissions has been submitted to and approved in
writing by the Local Planning Authority. The development shall not
be carried out otherwise than in complete accordance with the
approved details.
REASON - To achieve a satisfactory
form of development in the interests of climate change.
- No building shall be
constructed above damp proof course until precise details of the
bin stores have been approved have been submitted to and approved
in writing by the Local Planning Authority. The details shall
include the number, the location and design of the stores. The bin
stores shall be in place prior to the occupation of the building
and retained thereafter. The development shall not be carried out
otherwise than in complete accordance with the approved
details.
REASON - In the interests of the
general amenity of the development
- Prior to the
installation of any fixed mechanical ventilation system associated
with the development hereby approved the details shall be submitted
to and agreed in writing with the Local Planning Authority. The
ventilation system thereby agreed, shall achieve noise levels in
excess of 5dB below the background noise level (LA90, T) when
assessed in accordance with BS:4142. The agreed ventilation system
shall thereafter be retained and maintained throughout the lifetime
of the development.
REASON - In the interest of
safeguarding the amenities of the neighbouring
properties.
- Prior to the
commencement of the any phase of the development, including
demolition, a site specific Demolition and Construction Management
Plan shall be submitted to and approved inwriting by the Local
Planning Authority. The plans shall include the following, unless
the Local Planning Authority dispenses with any requirement[s]
specifically and in writing:
a.
Dust Assessment Report which assesses the dust
emission magnitude, the sensitivity of the area, risk of impacts
and details of the dust control measures to be put in place during
the demolition and construction phases of the development. The Dust
Assessment Report shall take account of the guidance contained
within the Institute of Air Quality Management “Guidance on
the assessment of dust from demolition and construction”
February 2014.
b.
Methods for controlling noise and vibration during
the demolition and construction phase and shall take account of the
guidance contained within BS5228 “Code of Practice for noise
and vibration control on construction and open
sites”.
c.
Construction Traffic Routes, including parking areas
for staff and visitors.
d.
Details of wheel washing.
e.
Road Maintenance.
f.
Warning signage.
The
development shall not be carried out otherwise in complete
accordance with the approved Plan.
REASON - In the interests of highway
safety and residential amenity
- No construction or
demolition activities, including the use of plant and machinery, as
well as deliveries to and from the site, shall take place outside
the hours of 08.00-18.00 Monday to Friday, 08.00-14.00 Saturday
with no activities on Sunday or Bank/Public Holidays without the
prior written permission of the Local Planning
Authority.
REASON - In the interests of highway
safety and residential amenity.
- If piled foundations
are incorporated into the development hereby approved, details of
the piling method including justification for its choice, means of
monitoring vibration, and groundwater risk assessment if necessary,
in accordance with recognised guidance, shall be submitted and
agreed in writing by the Local Planning Authority prior to works
starting on site. The development shall not be carried out
otherwise than in accordance with the approved details.
REASON - In the interests of the
amenity of the area
- No development shall
take place until the applicant has secured the implementation of
the programme of archaeological work in accordance with a written
scheme of investigation, which has been approved in writing by the
local planning authority as follows:
a)
Methodologies for a Historic England-style Level 2
building record prior to any conversion works or stripping out of
fixtures and fittings.
b)
A timetable of works in relation to the proposed
development, including sufficient notification and allowance of
time to ensure that the site work is undertaken and completed in
accordance with the approved strategy.
c)
Monitoring arrangements, including the notification
in writing to the County Durham Principal Archaeologist of the
commencement of archaeological works and the opportunity to monitor
such works.
d)
A list of all staff involved in the implementation
of the strategy, including sub-contractors and specialists, their
responsibilities and qualifications.
The development shall
then be carried out in full accordance with the approved
details.
REASON - To comply with National Planning
Policy Framework 2021 as the buildings are non-designated heritage
assets
- The development
shall not be occupied until the post investigation assessment has
been completed in accordance with the approved Written Scheme of
Investigation. The provision made for analysis, publication and
dissemination of results, and archive deposition, should be
confirmed in writing to, and approved by, the Local Planning
Authority.
REASON - To comply with Paragraph 205 of the NPPF, which
requires the developer to record and advance understanding of the
significance of heritage assets, and to ensure information gathered
becomes publicly accessible.
- Development shall be
implemented in line with the drainage scheme contained within the
submitted document entitled “Proposed Drainage Layout”
dated “25/01/2021”. The drainage scheme shall ensure
that foul flows discharge to the combined sewer at manhole 6101 and
upstream of 6204 and ensure that surface water flows discharge to
the combined sewer at manholes 6101 and slightly upstream of
manhole 6204. The surface water discharge rate at each connection
point shall be restricted to 2.5l/sec. The final surface water
discharge rate shall be agreed by the Lead Local Flood
Authority.
REASON - To prevent the increased risk
of flooding from any sources in accordance with the National
Planning Policy Framework 2021
-
The development hereby approved shall not be
commenced on site, until a scheme for ‘the implementation,
maintenance and management of a Sustainable Surface Water Drainage
Scheme has first been submitted to and approved in writing by the
Local Planning Authority. The scheme shall be implemented and
thereafter managed and maintained in accordance with the approved
details, the scheme shall include but not be restricted to
providing the following details.
a)
Lead Flood Authority Validation Checklist
b)
Detailed design of the surface water management
system.
c)
A build program and timetable for the provision of
the critical surface water drainage infrastructure.
d)
A management plan detailing how surface water runoff
from the site will be managed during the construction
phase.
e)
Details of adoption responsibilities.
REASON - To ensure the site is
developed in a manner that will not increase the risk of surface
water flooding to site or surrounding area, in accordance with the
guidance within Core Strategy Development Plan Policy CS16 and the
National Planning Policy Framework 2021.
-
The development hereby permitted shall only be
carried out in complete accordance with the approved Flood Risk
Assessment (FRA) & Drainage Strategy dated 4th June 2021 and
the following mitigation measures detailed within the
FRA
a.
Discharge to NWL combined sewers restricted to
5l/s
b.
708m3 of storage provided.
The
mitigation measures shall be fully implemented prior to the
occupation and subsequently in accordance with the timing / phasing
arrangements embodied within the scheme, or within any period as
may subsequently be agreed, in writing, by the local planning
authority.
REASON - To prevent flooding by
ensuring the satisfactory storage of / disposal of surface water
from the site and to reduce the risk of flooding to the proposed
development and future occupants.
-
The building hereby approved shall not be brought
into use until: -
a)
Requisite elements of the approved surface water
management scheme for the development, or any phase of the
development are in place and fully operational to serve said
building.
b)
Management and maintenance plan of the approved
Surface Water Drainage scheme has been submitted and approved in
writing by the Local Planning Authority, this should include the
funding arrangements and cover the lifetime of the
development.
REASON - To reduce flood risk and
ensure satisfactory long-term maintenance are in place for the
lifetime of the development.
- CL3
– Phase 2 Site Investigation Works.
- CL4 - Phase 3
Remediation and Verification Strategy.
- CL5 -
Construction/Remediation works.
- CL6 –
Implementation of Phase 3 Remediation Strategy and Phase 4
Verification and Completion Report.
- The development shall
not be carried out otherwise than in complete accordance with the
Tree Protection Plan and Arboricultural
Method Statement contained within the document entitled
“BS5837 Tree Survey – Darlington MSCP” dated
December 2020 and produced by Eco North unless otherwise agreed in
writing by the Local Planning Authority.
REASON - In the interests of the
visual appearance of the development.
- The development shall
not be carried out otherwise than in complete accordance with the
Mitigation and Compensation Strategy contained within the submitted
document entitled “Preliminary Ecological Appraisal & Bat
Roost Assessment Darlington MSCP” dated June 2021 and
produced by Eco North unless otherwise agreed in writing by the
Local Planning Authority.
REASON - In the interests of
biodiversity and habitats.
-
The development shall not be carried out otherwise
than in complete accordance with the Mitigation and Compensation
Strategy contained within the submitted document entitled
“Bat Survey Report Darlington Multi
Story Car Park” dated August 2021 and produced by Eco North
unless otherwise agreed in writing by the Local Planning
Authority.
REASON - In the interests of