Verbal update by the Assistant Director Community Services
Minutes:
The Assistant Director – Community Services informed Members that the CCTV replacement camera programme was agreed by Cabinet in June 2022, to upgrade the analogue cameras and transmission equipment to improve the quality and efficiency of the system.
Members were informed that the tender process would commence in January 2023 and the duration of the programme would be 3 to 6 months, with work completed by the end of 2023.
Following a question, the Assistant Director – Community Services advised Members that any disruption to the CCTV feed would be minimised to ensure no significant disruption during the replacement programme.
RESOLVED – That a further update be provided to a future meeting of this Scrutiny Committee, following the completion of the tender process.