Northern Powergrid have been asked to supply a
new trackside connection point by Network Rail. The supply is to be
via an underground cable through the rough access track which is
part owned by the council and also serves as access to council
owned track side land.
Northern Powergrid do have powers to requisition a wayleave if this
is not granted voluntarily.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 22/05/2023
Decision due: 12 Apr 2023 by Assistant Director Economic Growth
Contact: Guy Metcalfe, Head of Service for Asset Management and Investment Email: [email protected].
Consultation process
N/A