Advanced Design, Highways Maintenance, Northern Link Road, Darlington Station and the Town Centre - Approval of Capital Funding Release and Submission of Funding Bids and Expressions of Interest - Bids to NPIF and Challenge Fund

Guidance issued 24 July 2019 for the Local Highways Maintenance Challenge Fund by Department for Transport (DfT).
Following a review of highway asset condition data, the A68 was identified as a key corridor requiring maintenance – a combination of carriageway reconstruction, improving the skid resistance, improving gullies and drainage assets to manage surface water flooding and resurfacing the cycle route – both in the rural and urban areas as appropriate.
The bid for £2.260m was submitted on 30th October along with two other bids by TVCA, as a Tees Valley package of schemes. A decision by DfT was expected by end of December but this is now delayed due to the recent general election.
Guidance issued 24 July 2019 for the Local Pinch Point Fund (NPIF) by DfT. Following a review of the eligibility criteria and assessment process the A68 between Bondgate and A1(M) Junction 58 was selected as transport modelling work has already highlighted significant congestion issues on this corridor.
An Expression of Interest has been developed and will be submitted on 31st January 2020.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 31/12/2019

Decision due: 20 Dec 2019 by Director of Economic Growth and Neighbourhood Services

Contact: Ian Williams, Chief Executive Email: [email protected].

Decisions