Cabinet have requested that Officers look at
the retention of Darlington’s Central Library at Crown
Street, following this decision proposals have been developed to
improve the current building fabric and visitor experience.
Any works carried out at Crown Street Library will need to address
the long term issues with regard to the roof, structural,
mechanical & electrical as well as sympathetic refurbishment of
the building alongside improved access.
An element of the current development work is a Bat Activity Survey
to develop a robust ecological assessment and understanding of bat
activity within the building.
The initial survey will involve the installation of Static bat
equipment to be deployed within the roof void for a period of 5
days, to include the installation of cameras, following the 5 day
survey period ECOSERV will return to site and collect the
equipment, data can then be evaluated off site and a written report
submitted. 2 No further surveys will then be required at
approximately 3 week intervals.
It was considered that this survey work may have not been possible
due to the COVID 19 restrictions. However, guidance released by
Defra and the Chartered Institute of Ecology and Environmental
Management (CIEEM) states that ‘Ecologists and environmental
professionals should therefore be able to continue with outdoor
work, including ecological surveying and supervision, where they
can continue to follow Public Health England
guidelines’.
The Ecologists have developed preliminary risk assessments and
method statements that would enable the surveys to progress in
accordance with Public Health England’s guidance. These would
be developed further for approval if surveys are agreed to
progress.
The next stage would be to undertake 3 No Surveys approximately 3
weeks apart between May and September.
Financial/staffing/health & safety (including virus
transmission risks)/service delivery impacts/other risks and
impacts considered:
Programme - It is anticipated that the work will take up to 5 days,
this will include the installation and retrieval of the equipment
along with site visits by ECOSERV to carry out visual
surveys.
Communications - The building is in the ownership and is also
maintained by Darlington Borough Council, all parties have been
made aware of the survey times and dates.
Financial - The development work has been commissioned by
Darlington Borough Council.
COVID19 - The works can be progressed under the current guidelines
with the necessary systems in place. Access to the attic space will
be limited to ECOSERV personnel for the duration of the survey
period.
Equality Impacts:
Not applicable.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 25/11/2020
Decision due: 11 May 2020 by Assistant Director Community Services
Contact: Ian Thompson, Assistant Director Community Services Email: [email protected].
Consultation process
Councillor Kier, Cabinet Portfolio Holder for
Local Services.